The Making of the Channel
Tunnel
A
Modern Day Wonder
by John Neerhout, Jr.
It
is both a privilege and pleasure for me to share with you today a perspective
on one of the great technological accomplishments and civilization milestones
of this era - The Channel Tunnel.
When
I was invited to be the 1995 William R. and Erlyn J. Gould Distinguished
Lecturer, I was informed that this esteemed lecture series is designed to
provide insight and comment on the development of technology and its
relationship to the quality of life. I held the opinion, which I believe is
also shared by the Goulds, that these two elements must be intertwined if
mankind is to successfully advance while preserving the core values of human
culture.
In
many cases, the success of a project that initiates technological advances is
ultimately measured in terms of its contribution to the quality of life, to
society, the economy, or the environment. The technologist is therefore
required to maintain a broader perspective than just technological concerns.
The technologist, humanist, and opinion leader must maintain mutual respect
and cooperative exchange in order to understand each other's particular
concerns. Typically, it is the individual with the broadest perspective, in
most cases the technologist, who is most capable of managing this cooperative
exchange process. Successful projects rely greatly upon such
multi-dimensional or visionary individuals. In the engineering and
construction business, sensitivity to quality-of life concerns is a business
imperative. Sensitivity to and consideration for the community, environment,
and general public begin long before the design phase and remain a priority
throughout the construction phase as well as during project operation.
The
Channel Tunnel project had one of the longest gestation periods in history -
its ideas, plans, and efforts span well over two centuries. And, it may be
the best example and most complex one where technology issues were integrated
with those related to quality of life. Its challenges required the
technologists, the opinion leaders, and often the community itself, to be
very interactive in order to successfully overcome the multitude of issues.
In the time afforded, I will share with you some of the history and
challenges of this great project. Some of the challenges had more of a
technical solution, but many required the technologist to have a broad
perspective for quality-of-life concerns as well.
To
more fully appreciate this endeavor, permit me to start at its origin,
skipping a few decades in the interests of time, yet supplying sufficient
detail regarding the issues most critical to the project.
Eurotunnel
is a centuries-old dream come true! It is probably the most significant
international transport project since the Panama Canal, and the largest
project ever paid for entirely by private finance. Engineers have dreamed of
building a Channel Tunnel for at least 250 years. Between the dream and the
reality lay a dramatic and unimaginably complex engineering project.
"Linking
France and England will meet one of the present-day needs of
civilization," wrote French writer, Louis Figuier, in 1888. He was only
restating a conviction that had been expressed from time to time by many of
his compatriots for more than 138 years. Britain and France were the world's
leading maritime and commercial powers, and they were a mere 34 kilometers
apart. Yet, trade between them was an extremely hazardous affair. The
shortest route - across the Pas de Calais or Straits of Dover - was also the
most difficult. Travelers making the current- and storm- besieged crossing
could, with a fair wind and a skillful captain, be at their destination in
six or seven hours. They could equally be delayed days or weeks and be
extremely seasick by the time they reached the opposite shore. So, early on,
quality-of-life issues spurred on engineering imagination.
The
first recorded proposal was in 1750, when the Academy of Amiens launched a
competition to find a way of improving the means of crossing the English
Channel. The prize was awarded the following year to the engineer, Nicolas
Desmarest. Many were surprised that the Academy found his proposal practical
enough to win the competition because what he suggested was a tunnel! No
major tunneling efforts had been undertaken since the time of the ancient
Egyptians and the Romans, both of whom had large slave work forces at their
disposal. It was significant that even in 1750 a tunnel was considered the
most practical solution, despite its technical and economic difficulties.
The
French continued to entertain thoughts of a fixed link as a reliable means of
conveying passengers and transporting goods across that treacherous
34-kilometer stretch. Half a century later, encouraged by Napoleon, a French
mining professor, Albert Mathieu-Favier, also proposed a tunnel between
Britain and France. Lighted by oil lamps and ventilated by chimneys at
regular intervals, the plan included an artificial island in mid-Channel for
changing horses. Napoleon was fascinated with this idea, and in 1803 an
Anglo-French group was formed to build the tunnel. However, many British
citizens and their political and military leaders were suspicious of
Napoleon's motives and would not cooperate, so the tunnel project became a
casualty of the Napoleonic Wars.
In
fact, for most of the two-and-a-half century history of cross channel
projects, the British were less enthusiastic about a fixed link than the
French. Perhaps Shakespeare summarized the British sentiment best in Richard
II when he wrote the following patriotic vision of England:
This precious stone set in the silver sea,
Which serves it in the office of a wall,
Or as a moat defensive to a house,
Against the envy of less happier lands.
The
Channel has on many occasions protected the English from their enemies by
foiling invasion attempts, most notably the Spanish Armada in 1588 and again
in the dark days of 1940 when Hitler's armies overran Northern Europe. But
more important than the physical separation of Britain from the Continent was
the psychological separation. For centuries, the English regarded them selves
as distinct from and superior to their neighbors "across the water.
" They were semi- detached, part of Europe when it suited them, distinct
from Europe when it did not.
Among
engineers, enthusiasm for the tunnel was undiminished. However, to meet with
any success, they needed the right political climate and the ability to
communicate and sell their ideas to political players. From the 1830's
several schemes gained impetus through the efforts of another French
engineer, AimÊ ThomÊ de Gamond. He made the first geological and
hydrographical surveys of the route and tried to promote a succession of
projects to Napoleon III and Prince Albert, husband of Queen Victoria. He was
joined by a number of British promoters, including distinguished noblemen,
but for a variety of reasons none of the proposals came to fruition.
In
1881, Sir William Watkin began exploratory work at Shakespeare Cliff near
Dover. His Anglo-French Submarine Railway Company was associated with a
French group that included Alexandre Lavalley, contractor for the Suez Canal.
In 1883, using a Beaumont-English tunnel boring machine, pilot tunnel work
began at Dover, with a tunnel 2.13 meters in diameter, and 1,893 meters long.
A similar effort was started in Sangatte, France, west of Calais, with a
tunnel 1,669 meters long; however, that project too was abandoned, once again
defeated by influential British military and political opposition concerned
with Britain's national defense.
The
issue of national defense was not finally set aside until after World War II.
Even then, the British Government was not prepared to finance a fixed
cross-Channel link. A further attempt launched by British Prime Minister
Edward Heath in 1973 was abandoned by the incoming Harold Wilson government
in 1975. But the pressure from contractors and bankers for a variety of
tunnel or bridge schemes continued unabated. Many sectors of the British
public were convinced of its importance and its inevitability.
Among
these was the British business community. As trade within the European
Community increased, it found itself falling further and further behind its
continental competitors. A major reason was the cost of transporting goods
across the Channel. It was not just a question of ferry charges but also the
time factor. A freight truck could be driven from the Midlands to Dover,
Folkestone, or Newhaven in four or five hours. Once there, however, it could
be delayed as long or longer before being able to proceed those few
exasperating kilometers between Britain and France. In fact, the ferry
crossing was no quicker in 1975 than it had been in 1875.
Almost
as frustrated were the business travelers. The air route between Paris and
London is the busiest in Europe. Traveling between the two capitals could
consume almost an entire working day, considering the time spent waiting in
crowded terminals and going to and from airports to the city centers. The
question often arose as to how much time - and therefore money - could be
saved if the journey could be done in a few hours on a comfortable train in
which one could work, make phone calls, and even conduct conferences. Traffic
forecasts predicted the situation to worsen. Total cross-Channel passenger
demand was expected to increase by more than 300 percent by the end of this
century, and freight traffic demand was expected to increase by almost 400
percent over the same period.
Although
it did not seem so at the time, the election in 1979 of Margaret Thatcher's
government meant the Channel Tunnel's time had finally come. New political
imperatives turned what had been a public works plan beyond hope into a private
enterprise almost beyond praise. A grand physical link between Britain and
France funded from the private purse became an icon for Thatcherism as well
as a symbol of European unity.
Meeting
at Avignon in 1981 for one of their regular economic summits, British Prime
Minister Thatcher and French President Francois Mitterrand agreed to setup an
official working group that would examine the question. Mrs. Thatcher
described the Tunnel as "a project that can show visibly how the
technology of this age has moved to link the Continent and Britain closer
together." For her, the Tunnel would boost the private commercial sector
and provide tangible evidence of her commitment to the ideal of national
recovery spearheaded by free enterprise. From the outset, she stipulated that
no government money would be available. In France, the Tunnel was one of
several major infrastructure developments initiated in the early years of
President Mitterrand's first term in office. The President was following
several of his predecessors in giving his personal stamp of approval to a
project designed to create nationwide economic and technological benefits.
However, the major difference in this case was that the state would not have
any financial involvement. In addition, the Tunnel would also help to
revitalize the run-down, economy of northwest France, which was experiencing
high unemployment and was missing out on the fast growing economic prosperity
enjoyed by the rest of France. For both leaders the Tunnel offered an opportunity
to leave a permanent legacy of their time in office.
This
summit initiative led to a series of technical and financial studies and to
the development of tunnel and bridge schemes by different engineering groups.
Finally, on April 2, 1985, the British and French governments issued a formal
invitation for potential promoters to compete for the Channel fixed link. The
closing date for submissions was midnight on October 31, 1985. Attached to
each invitation were more than 60 pages of guidelines setting out the
competition rules. Each proposer's financial plans were to be presented,
including amounts of cash to be raised and money already promised. The link
would be constructed and operated at the risk of the chosen promoter, which
would be free to decide its own commercial policy, tariffs, and the type of
service to be offered.
By
the October 31 closing date, nine schemes had been submitted. Four were
considered worthy of close scrutiny. These were: a motorway suspension
bridge, a tunnel accommodating a road and a railway, a combined bridge and
submerged tube system, and a tunnel to carry through- trains and shuttles for
road vehicles. In January 1986, the winner was the train/shuttle tunnel
devised by the consortium Channel Tunnel Group Limited - France-Manche S.A.
(CTGFM). This proposal later came to be known as "Eurotunnel."
Shortly
after the announcement, the two governments gave their reasons for selecting
the scheme of CTG-FM and awarding them the concession for construction and
operation of the system. The reasons were centered largely on financing and
practicality. Their scheme also carried the fewest technical risks and was
the safest from the travelers' point of view - thus creating a harmonious
advance in both technology and the quality of life. Unlike a bridge, it would
not create any maritime problems, and it was considered the least vulnerable
to sabotage and terrorism. Even in the more conventional schemes, technology
was unable to overcome the enormous difficulties posed by a drive-through
link. Among these were the problems of safe tunnel ventilation, of measures
to deal with the consequences of traffic accidents, and the probability that
many drivers would become mesmerized in a tunnel of this length.
It
was in Canterbury on February 12, 1986, that Thatcher and Mitterrand signed
the Treaty of Canterbury, which laid down the legal, financial, and
administrative bases on which the two nations would cooperate. Legislation
still had to pass through the national parliaments before finances could be
raised, and it was by no means certain that the representatives of the
British and French people would support the fixed link. However, government
determination and general enthusiasm among parliamentarians were strong
enough for the measure to easily pass. In France, two special procedures were
used, a Declaration d'Utilite Publique and a Procedure Grand
Chantier, which increased central, as opposed to local, support in the
national interest and helped with auxiliary infrastructure, staff training,
etc. In the UK, the necessary legislation went through as a so-called Hybrid
Bill, that is, a Public Bill with additional private enterprise sections.
During these legislative processes, the engineers were frequently called in
to deliver technical dissertations in layman's terms in order to satisfy both
political and public concerns, once again playing a role outside strict
engineering. By May 6, 1987, the process in France was complete. In Britain,
it took a little longer, but the Channel Tunnel Act received the Royal Assent
on July 23, 1987. Now, at last, the Treaty of Canterbury could be formally
ratified and CTG-FM could be given the final go-ahead.
Initially,
CTG-FM consisted of a consortium of the British joint-venture, the Channel
Tunnel Group, and the French jointventure, France Manche. The Channel Tunnel
Group was made up of five British contractors and three British banks, and
France Manche was made up of five French contractors and three French banks.
Prior to winning the concession, the shareholders of CTGFM realized that they
would have to separate the roles of owner/operator and constructor. CTG-FM
had to become a client for financing, owning, and operating the project and a
contractor for designing, constructing, and commissioning it.
On
July 8, 1985, an agreement was signed between Translink Contractors, a
joint-venture subsidiary of the five British construction companies in CTG,
and Transmanche Construction, a similar grouping of the five French contractors
in France Manche. The agreement stated that Translink and Transmanche had
come together to prepare a proposal for the design and construction of the
fixed link, "for submission to and agreement by the promoter," that
is, CTG- FM. Translink and Transmanche would carry out the work as a fully
integrated, 50/50 joint- venture. That joint-venture would carry the work
under the name Transmanche Link (TML).
The
CTG-FM consortium also metamorphosized itself into an owner/operator group by
forming the umbrella holding companies, Eurotunnel S.A. (in France) and
Eurotunnel P.L.C. (in Britain), with the shareholding of the contractors and
banks diminishing as Eurotunnel transformed itself into a separate
independent company.
A
contract for the design, construction, and commissioning of the complete
tunnel system was then negotiated between Eurotunnel and TML. The
"protocol" agreement between TML and its client Eurotunnel (then
CTG-FM) in October 1985 was intended to be the basis for a design-and- build
contract if CTG-FM'S proposal for a Channel tunnel was successful. It made
use of Federation Internationale des Ingenierurs-Conseils conditions,
suitably amended for design- and-construct purposes, while retaining
provision for unforeseen ground conditions. As the Channel Tunnel project
moved towards reality, the finance people looked more closely than ever at
the proposed contract documents. What they saw made them uneasy. They
suspected that the contract was weighted heavily towards the contractors that
had originally written it, giving TML too much freedom and too little risk.
Consultants were called in to advise. One consultant reported that the
project was well conceived and technically feasible, but that the
construction contract lacked sufficient incentives for TML to make "every
reasonable effort" to finish on time, and failed to provide "the
necessary authority for the employer to enforce timely completion. " On
August 13, 1986, the contract was finally signed. Negotiations continued,
however, and the document was subsequently amended twice, much in
Eurotunnel's favor, during the six months that followed.
In
financial terms as much as in engineering, the Channel Tunnel is an
unprecedented venture: a transport infrastructure project developed and
financed by the private sector alone, without any form of financial support
from either the French or British governments. A complex financing scheme
formed an integral part of the original submission presented by CTG-FM to the
French and British governments. The scheme provided for the cost of the
Tunnel to be financed by S5 billion worth of bank loans, with equity of an
additional S1 billion coming from the promoters, institutional investors, and
a public share flotation.
Preliminary
equity financing was raised in two main stages, known as Equity 1 and Equity
2, in September and October 1986, respectively. The $47 million Equity 1 was
a placing of cash by the founding shareholders to kick off project funding.
The S206 million Equity 2 came principally from French and British investment
institutions. The mammoth task of negotiating a banking credit agreement and
organizing Equity 3 took more than a year. The banks agreed to underwrite the
credit agreement in August 1987. The S770 million Equity 3, the project's
first call on public money, required simultaneous listing on the Paris and
London stock exchanges - stock markets with totally different traditions and
procedures. This was the first time such an exercise had been carried out. To
add to the challenge, Eurotunnel's stock market launch went forward on
November 16, 1987, shortly after the stock market crash of October 19, also
known as "Black Monday. " Postponing the share issue could have
been fatal for the project. However, dividends were not expected to be paid
until some years after the opening of the Tunnel, so the investment was
longer term than the current difficult market situation. In the end, over
300,000 investors (two-thirds of them in France) bought shares; the
underwriters stepped in to pick up the balance which was not applied for by
the public. Being extremely sensitive to public opinion and feasibility
scrutiny, engineering experts prepared both the technical prospectus and a
memorandum of understanding with the banks in order to win the confidence and
support of future investors and future lenders.
Design
engineering was probably the most anticipated challenge of this mammoth
project but almost the easiest to meet. That is not to downplay this
engineering marvel, but solving the logistical, financial, environmental, and
other problems were major hurdles too. In terms of a pure tunneling exercise,
however, the fixed link called for proven tunnel boring techniques combined
with some enhanced design features. Let me share with you a brief design
overview of the tunnel system.
The
Eurotunnel system has three concrete lined parallel tunnels approximately 50
kilometers long running mostly undersea but also under land at either end
approaching their English and French portals. The undersea sections of the three
tunnels are the world's longest and run for 38 kilometers under the English
Channel. The longest rail tunnel in the world, Japan's Seikan tunnel linking
the islands of Hokkaido and Honshu, is nearly 4 kilometers longer overall
than Eurotunnel's, but its undersea section is only 23 kilometers.
The
two outside tunnels (rail tunnels) have an internal diameter of 7.6 meters
and carry both through and shuttle trains. The center tunnel has an internal
diameter of 4.8 meters and is utilized as a service tunnel with its own mini
transportation system. The two rail tunnels were excavated 30 meters apart
and no closer than 8 meters to the walls of the center service tunnel.
The
service tunnel is linked to the rail tunnels by cross-passages every 375 meters;
the rail tunnels are further connected by piston relief ducts every 250
meters to spill air pressure, generated by the high-speed trains, from one
tunnel to the other. There are also two enormous undersea crossover caverns
where the rail tunnels are brought together, making it possible for trains to
cross from one track to the other. The crossovers divide the length of the
rail tunnels into three equal sections, any of which can be closed off in an
emergency or for maintenance. To maintain separation for ventilation
purposes, the two crossover caverns are divided longitudinally by huge pairs
of sliding doors. Interlocked with the signaling system, they are only opened
to permit trains to switch from one running tunnel to the other.
The
tunnel system is kept dry by five pumping stations and sumps, three built
under the sea and one on each shore. An unusual feature in the rail tunnels
is the installation of a cooling system designed to counteract the buildup of
heat produced by fast-moving trains. Chilled water is pumped through cooling
pipes so that the tunnel air is maintained at a comfortable temperature.
There
are terminals at each end of the system. The British terminal is located at
Cheriton, near Folkestone in Kent, and the French terminal is located close
by the Pas-de-Calais village of Frethun. The French terminal area measures
480 hectares (1,186 acres), and the British terminal, limited in size because
of geographical constraints, covers an area of 140 hectares (346 acres). The
main features of both terminals are the long parallel shuttle platforms
linked by ramps to overpass bridges. To speed up operations at the terminal,
the 800-meter-long shuttle trains are loaded and unloaded in two sections
(front and rear), each with its own boarding and exit points. These two
sections, or these boarding and exit point sectors, are served by two access
overpass bridges and two exit overpass bridges from which a road leads
directly to the motorway. Other notable features of the terminals are the main
control buildings, where the rail and road traffic system is managed, and the
principal maintenance building at the French terminal, where all Eurotunnel
rolling stock is serviced.
After
extensive geological surveying, the route of the three tunnels was drawn to
run mainly through a layer of soft impermeable (or waterproof) rock called
chalk marl. It would be hard to find a better medium for tunneling purposes.
The chalk marl allowed the tunnel boring machines (TBMs) starting from the
British coast to be designed for a rapid advance, and these TBMs often
completed over 300 meters of tunnel in a week. Near the French coast, there
is a stretch of fissured water-bearing ground. To overcome this difficulty,
slower and more complex TBMs, that could operate in a sealed mode under water
pressure, were used.
The
tunnels were all lined with pre-cast concrete segmented rings, except for
areas of poor ground or at tunnel connections or intersections, where ductile
iron linings were used. Both of these construction materials are familiar to
tunnel builders, but particular care was given to their manufacture to ensure
the highest quality standards. The concrete specified was of very high
strength and density in order to give protection to the steel reinforcement;
secondary protection against corrosion was also provided through surface
coating and arrangement for cathodic protection. In designing the tunnel
lining, a total of 18 design development studies were carried out to ensure
that no aspect of the system's operation was overlooked. In addition, the
lining was also designed for a 120 year life, which meant that no significant
deterioration in performance could occur over a period of 120 years.
Considerations
of passenger safety drove almost all of the major decisions about the design
and operation of the Tunnel. It was recognized from the beginning that a
continuous tunnel under the sea would require special measures to ensure an
adequate level of safety. Standards would have to be more rigorous than for existing
rail tunnels. But the fact that it was a new project enabled Eurotunnel to
build safety in from the very start, an advantage over adding safety measures
to an existing system. For modern railways, the record shows that levels of
safety achieved in long tunnels are so high that it is almost impossible to
derive meaningful death and injury rates from accident statistics. From an
operations perspective, the triple bore system provided a significant safety
advantage. The risk of a derailed train being struck by one coming the other
way is eliminated. Access by maintenance staff to sections of the tunnel
carrying trains can be avoided as maintenance or repairs can be planned at
night with two-way travel proceeding through the other bore. Safety during construction
also contributed to the decision to build separate tunnels for each of the
two rail lines, giving rise to a smaller tunnel diameter, and maximizing the
cover of sound rock around the tunnel. A further advantage of multiple
tunnels is that the number of emergency escape routes is increased, an
advantage during both construction and operation. Due to these and other
safety considerations built in to system design and operation by its
engineers, Eurotunnel is believed to be one of the safest transport systems
ever conceived.
Environmental
sensitivity went hand-in-hand with safety and was equal in its influence on
design and operation of the tunnel. Before work began, baseline studies of
all the affected areas were completed to establish the state of the
environment on and around all construction sites. This was followed by
ongoing management and monitoring, which continues today. The country on each
side of the Channel has been continuously occupied for over 12,000 years and
is immensely rich in archaeological content. Archaeological and geological
research of various sites revealed fascinating histories with evidence of
Neolithic, Bronze Age, Iron Age, Roman, and Medieval settlements. A
relocation program to preserve and protect rare species of plant and animal
life was also carried out. Under the terms of the Channel Tunnel Act, the
local planning authorities, although they could not prevent the building of
the fixed link and its terminals and related transport systems, had
considerable powers to shape development details. For example, the Act
required Eurotunnel to agree to specific statements on minimizing disruption
caused during the construction period by noise, dust, the transportation and
storage of bulk fill materials by road and rail, as well as night-time
working. Eurotunnel also had to agree to a landscape scheme for each of the
permanent works, as well as for the reinstatement of temporary work sites.
Before granting approval, the local planning authorities were required by the
Channel Tunnel Act to consult fully with the residents of the area, with
various statutory bodies, and relevant preservation societies. Once again, it
was the technologist working hand-in-hand with the community to understand
and resolve concerns regarding the environment.
The
project achieved tunnel breakthrough, that is, the first establishment of a
through passage on December 1, 1990, thus creating the first land route
between England and France for more than 12,000 years. It took another three
years to complete the project for commissioning. On December 10, 1993, less
than six and a half years after ratification of the Treaty of Canterbury, TML
handed the Channel Tunnel over to Eurotunnel. In that short time - less than
it takes to plan, approve, and build a motorway - the Channel Tunnel was
completed and almost ready for business. By then, work on the project had
totaled more than 170 million man hours. Finally, on May 6, 1994, the two
countries' Heads of State - Queen Elizabeth II and President Mitterrand - officially
opened the Channel Tunnel to the public. Almost all of the obstacles and
difficulties that seemed to stand in the way of this immense project were now
in the past.
The
Channel Tunnel is no ordinary project. The four types of cross-channel service
that the Tunnel offers - conventional freight and passenger trains, plus two
types of road vehicle shuttle will, in due course, make it the busiest
railway in the world. Passenger service trains are timed to pass through the
Tunnel in 21 minutes. The passenger vehicle shuttle train can go from
terminal to terminal in 35 minutes. The average shuttle journey time, from
arriving at one Tunnel terminal to departure from the other, is estimated to
be 65 minutes, with an estimated peak departure frequency of four departures
per hour. That is almost half the coast-to-coast travel time of the fastest
cross-channel ferry, with more than three times the rate of departures. After
just one year in operation, the freight shuttle service has reached the
number one position on the Folkestone/Dover-Calais cross-channel route,
taking 35 percent of the market. In addition to the diversion of the forecast
global demand, the existence of the Tunnel will create some additional
traffic that would not otherwise cross the Channel. By the year 2003, it is
estimated that the Channel Tunnel will induce approximately 7.7 million
passengers in terms of created passenger traffic and 2.7 million gross tonnes
of created freight traffic.
So
its impacts on the business commuter, the shipping and rail industries, and
likely the economies of the surrounding communities are great. Commute time
is cut in half and offered three times more frequently passenger and freight
traffic is increasing; and the depressed industrial areas around the French
and British terminals are expected to benefit from the increased traffic.
Many other benefits and effects on social systems have yet to be charted.
G.K.
Chesterton said, "You make your own friends and you make your own
enemies, but God gives you your neighbors." Without any doubt, the
Channel Tunnel will alter the face of Anglo- French travel in the near
future. It caused the coming together of two communities joined for the first
time since the Ice Age by a single fixed land link. It has made the dream of
many great dreamers and visionaries over the last two and a half centuries a
reality. It is a great engineering feat and a major project with lasting
benefits to many communities.
Let
me close with a point I made at the start - the success of a project that
stimulates technological advances is often measured by its contributions to
the quality of life - to society, the economy, or to the environment. And, as
I have illustrated in the example of the Channel Tunnel project, it was the
technologist, in most cases an engineer, who had to bridge the diversity of
issues, who became, as necessary, an educator, an environmentalist, a
financier, a politician, a diplomat, or a local community advocate to ensure
the success of such a vast project. So must the technologist be in all
endeavors versatile and with broad perspective. The architect and inventor,
Buckminster Fuller, perhaps realized the need for a broader vision when he
said, "When I am working on a problem, I never think about beauty. I
think only of how to solve the problem. But when I am finished, if the
solution is not beautiful, I know it is wrong. " Let's continue to
strive for beautiful solutions.
Thank
you.
This original lecture was given in the Saltair Room, Olpin Union Building
at the University of Utah.
October 5th, 1995.
|